Project Update: Progress towards Completion of Yeriwah Clinic

Project Update: Progress towards Completion of Yeriwah Clinic March 23, 2024

In the ever-evolving landscape of healthcare infrastructure development, the Yeriwah Clinic project is a testament to dedication and progress. As we approach the final stages of construction, it is with great pride and enthusiasm that we present an update on the project’s advancement as of March 23, 2024.

Electrical Work: The backbone of any modern healthcare facility, the electrical infrastructure of Yeriwah Clinic, is now 95% complete. Our skilled technicians have meticulously installed wiring, lighting fixtures, and power outlets, ensuring optimal functionality and safety throughout the premises.


Interior Painting: The vibrant hues and soothing tones that adorn the clinic’s interior have reached a completion rate of 90%.

Floor Tiling: The foundation upon which the clinic’s operations will stand, the floor tiling, has achieved an impressive completion rate of 95%.

Plumbing: At 70% completion, the installations signify the intricate network sustaining the clinic’s essential functions. From water supply to drainage, our team has worked diligently to ensure seamless operations and optimal resource management.

Ceiling Installation: The canopy that shelters and enhances the clinic’s interior space is now 90% complete. With precision and skill, our contractors have installed ceiling panels that not only provide structural support but also enhance acoustics and aesthetics.

Soak-Away System: The foundation of sustainable healthcare infrastructure, the soak-away system, has reached the halfway mark at 50% completion. This critical component ensures proper disposal of wastewater, minimizing environmental impact and promoting hygiene standards.

Additional Installations:
Beyond the core components of construction, essential installations have been completed to further enhance the clinic’s functionality and security. Ceiling fans, a necessity in tropical climates, have been fully installed, providing comfort to patients and staff alike. Additionally, the CCTV surveillance system has been implemented, ensuring the safety and security of all within the clinic premises. The installation of air conditioning units, vital for maintaining optimal temperature and air quality, is now at 70%, nearing completion.

Next Steps:
As we near the final stages of construction, our focus shifts towards meticulous completion and quality assurance. In the days ahead, we will: Conclude the remaining 5% of electrical work to ensure seamless operation of all systems. Finalize the interior painting, tiling, plumbing, and ceiling installations to bring the clinic to its operational readiness. Complete the installation of the soak-away system to uphold hygiene standards and environmental sustainability. Ensure the successful completion of air conditioning installation to provide optimal comfort for patients and staff.

In conclusion, the Yeriwah Clinic project exemplifies our unwavering commitment to excellence in healthcare infrastructure. We extend our gratitude to all involved stakeholders for their support and collaboration as we strive towards the realization of a facility that will serve the community with distinction