Construction Progress:
Floor Tiling: The floor tiling project has reached a significant milestone, with 95% of the work completed. The team has been meticulous in ensuring a high-quality finish, and we anticipate the full completion of this phase shortly.
Soak-Away Concrete: Work on the soak-away concrete is progressing as planned. The team is dedicated to meeting the necessary standards, and we expect completion in line with the project schedule.
Perimeter Fence: Approximately 95% of the perimeter fence has been successfully erected, contributing to the security and privacy of the clinic. The team is actively working on the remaining 5% and is committed to completing it in a timely manner.
Interior Work:
Ceiling Installation: The installation of the ceiling has commenced, enhancing the structural and aesthetic aspects of the clinic. This development adds to the overall functionality and appearance of the facility.
Interior Painting: The first layer of interior painting is at an advanced stage, with 90% of the work completed. The selected colors and finishes are creating a warm and inviting atmosphere within the clinic.
Glass Door Installation: Glass doors for some rooms have been successfully installed, contributing to both the functionality and aesthetic appeal of the clinic.
Next Steps:
- The construction team will finalize the remaining 5% of floor tiling, ensuring a comprehensive and polished finish.
- Ongoing efforts will continue on the soak-away concrete and the completion of the perimeter fence.
- The installation of the ceiling and the interior painting will progress to subsequent layers as planned.
- Further installations, including additional glass doors, will be carried out in alignment with the project schedule.