Project Report Update – Yeriwah Clinic – February 4, 2024

Construction Progress: Electrical Work: Substantial progress has been made on the electrical work, with approximately 90% of the tasks completed. The team has diligently ensured that all electrical systems are installed safely and according to specifications. Interior Painting: The interior painting project is halfway through, with 50% of the work completed. Efforts are ongoing to …

Project Report Update – Yeriwah Clinic Construction (January 3, 2024)

We are pleased to provide a comprehensive update on the ongoing construction at Yeriwah Clinic. Significant progress has been made since the last update. Air Conditioning Installation: The AC company has made significant strides, supplying materials, and commencing the installation of air conditioning systems. The pipe-laying process is underway, ensuring optimal functionality. Tiling Process: Tiling …