Project Report Update – Yeriwah Clinic – February 4, 2024

Construction Progress: Electrical Work: Substantial progress has been made on the electrical work, with approximately 90% of the tasks completed. The team has diligently ensured that all electrical systems are installed safely and according to specifications. Interior Painting: The interior painting project is halfway through, with 50% of the work completed. Efforts are ongoing to …